2024 Infrastructure Improvement Program

Arthur - North of Junction
Check back here for more information throughout the project.

Maple St. - Between Deer & Harding
Beginning on Wednesday, May 22, 2024, you will see crews beginning to work on your street.
 
We anticipate work to begin as soon as 7:00 A.M. on Wednesday. Work begins with milling of the existing asphalt road surface and adjusting the manhole structures.
 
Please have your vehicle(s) off the road by 7:00 A.M., Wednesday, May 22, 2024 so as not to interrupt the milling process. Driveway access during the milling will be restricted to allow for the crews to work safely and efficiently.
After the milling process is complete, access to the street will be allowed on the road base.
 
During the milling process, please park on the nearest side streets (Hamilton, N. Union, Deer, Harding, etc.). By the end of the day, the milling process will be completed and you may park as usual.
 
Weather, site conditions, etc. may impact the timeline for the work. We will continue to provide status updates throughout the project.


S. Union St. - Between Church & N. Union
Beginning on Wednesday, May 22, 2024, you will see crews beginning to work on your street.

We anticipate work to begin as soon as 7:00 A.M. on Wednesday. Work begins with milling of the existing asphalt road surface and adjusting the manhole structures.

Please have your vehicle(s) off the road by 7:00 A.M., Wednesday, May 22, 2024 so as not to interrupt the milling process. Driveway access during the milling will be restricted to allow for the crews to work safely and efficiently.
After the milling process is complete, access to the street will be allowed on the road base.

During the milling process, please park on the nearest side streets (Hamilton, N. Union, Deer, Harding, etc.). By the end of the day, the milling process will be completed and you may park as usual.

Weather, site conditions, etc. may impact the timeline for the work. We will continue to provide status updates throughout the project.


Sunset - Between Penniman & Junction

Beginning on Tuesday, May 21, 2024, you will see crews beginning to work on your street.

We anticipate work to begin as soon as 7 a.m. on Tuesday.   Work begins with milling of the existing asphalt road surface on Sunset and adjusting the manhole structures.

Please have your vehicle(s) off the road by Tuesday, May 21, 2024 at 7 a.m.  so as not to interrupt the milling process.  Driveway access during the milling will be restricted to allow for the crews to work safely and efficiently.

After the milling process is complete, access will be allowed on the road base.

Please park on the nearest side streets tomorrow during the milling process (Junction, Blanche, etc.).  By the end of the day, the milling process will be completed and you may park as usual.

Weather, site conditions, etc. may impact the timeline for the work. We will continue to provide status updates throughout the project.

Resident Meeting May 14, 2024

The City of Plymouth is hosting a residents meeting for the following streets:

Arthur - North of Junction
Maple St. - Between Deer & Harding
S. Union St. - Between Church & N. Union
Sunset - Between Penniman & Junction

The meeting will be held on Tuesday, May 14, 2024 at 6:00 PM at City Hall (201 S. Main St. 2nd Floor)

City staff and representatives from the City's Engineering firm will be on hand to explain schedule, details, and answer questions regarding the 2024 Infrastructure Improvement Program.

Please note that these streets are the first set of streets included in this year's project areas. Additional resident meetings will be held for the other streets closer to the start of the projects in our other areas.

Resident Information Packet