Harvey St. Construction Update September 13, 2021
Published on Sep 13, 2021 13:43
Monday, September 13, 2021
Hopefully you were able to enjoy the Fall Festival and the offerings
of the service clubs, including the pancake breakfast by the Kiwanis
Club and the Rotary Club’s Bar-Be-Que Chicken dinner.
Crews were back bright and early on Monday to continue the Harvey St.
project. Monday will be a long day for the crews as they will be making
the first connection of the new water main to the system. In addition,
crews will be working into the evening to connect the Arbor Health
building to the new system but won’t begin that process until after
public hours at the building. There will be some temporary
water service interruptions for a small group of businesses during the
day on Monday. Each of the businesses affected have been notified
personally and coordinated with for this step of the process. Unless you
have been personally contacted by the city for a temporary service
interruption on Monday, it is anticipated that your water will continue
to be in service as normal.
On Tuesday morning, crews will be connecting the water service lines
for the businesses along Harvey St. between Ann Arbor Trail and Penniman
to the new water main. There will be temporary water service
interruptions for only those businesses being connected and they have
all been notified and coordinated with for this step in the process.
In addition, crews will also begin excavation of the intersection of
Ann Arbor Trail and Harvey. This will create detours in the following
areas:
Northbound Harvey will detour at Wing St. to either Main St. or McKinley/Evergreen
Southbound Harvey will detour at Penniman/Church to Main St.
Eastbound Ann Arbor Trail will detour at McKinley to Wing St.
Westbound Ann Arbor Trail will detour to Main St. or Forest Ave.
We understand there are residents and business within the detour area
and travel will be permitted to local traffic in those areas; however,
the through traffic will need to follow the posted detours. There will
be additional signage indicating the detour route as well as barricades
signifying the limits of the construction zone.
To visually represent this next phase in the project, you can view the 2021 Infrastructure Improvement Packet Traffic Stage 3 map which can be found by clicking on the link.
In addition, we have prepared a diagram showing the detour route
while the intersection of Ann Arbor Trail and Harvey is closed to
through traffic. You can view that map, by clicking on the following
link: 2021 Ann Arbor Trail and Harvey Detour Map.
Should you have any questions, please contact the Department of Municipal Services at 734-453-7737 or [email protected]
|