Update for the 2021 Street Construction Program
Published on May 14, 2021 15:24
Crews are finishing the installation of the new water main on Hartsough and plan to begin pressure testing and disinfecting the pipe beginning today. The testing will be going on through the weekend and early next week. The crews will begin connecting the new water main to the rest of the City water system next week.
Work on the sanitary sewer main repair on Jener between Linden and Wing is scheduled to begin on Friday.
Please be cautious around the equipment and materials located throughout both project areas.
If you have any questions please call Municipal Services at 734-453-7737 x0
|